66 kV Cable Main Insulation Fault Test Conducted in Mozambique

Aug 30, 2024

Ⅰ.Preparation before testing

Test time 2024/7/22
Test location Mozambique, Africa
Laying method Direct burial
Both ends One end is located at the outdoor terminal of the substation, and the other end is connected to the indoor GIS within the substation.
Instrument used T8 Cable Fault Location System
Basic site information Two circuits of 66 kV cables are connected in parallel at both ends to the same terminal positions. At present, the two cable terminals at the outdoor end have been separated, while the GIS end remains short-circuited (RR, SS, TT). Each circuit is approximately 2.8 km in length and consists of single-core aluminum conductors with a cross-sectional area of 630 mm², arranged in a three-phase configuration (R—Yellow, S—Green, T—Red). There are three joints along the cable: two insulated joints and one straight-through joint. The section from the outdoor termination to the straight-through joint is cross-bonded, while the sheath of the straight-through joint and GIS terminal is directly grounded. The cable was not yet in service. Prior to commissioning, a DC withstand voltage test at twice the phase voltage was successfully completed. During initial energization, a fire broke out at the metal shielding of the straight-through joint, even before any breakdown of the insulation occurred. Power was not interrupted before the failure. A few minutes later, main insulation breakdown occurred, and the metal sheath at the straight-through joint location caught fire and was severely damaged. After the damaged joint was cut off and re-terminated, the cable failed again—this time instantaneously upon re-energization. The outer appearance of the straight-through joint remained visually intact, without any visible signs of failure. Insulation resistance tests showed that Phase R remained in good condition, while the insulation resistance between Phases S and T measured zero. The task now is to locate and identify the main insulation fault between Phases S and T.

 

Ⅱ.Test process

Step 1: Determine the nature of the fault

Insulation resistance measurements of R, S, and T phases were conducted using a megohmmeter, and the fault characteristics were determined as follows: A main insulation fault was identified between phases S and T (ST).

The test was performed from the outdoor termination at the substation. (Note: Since RR, SS, and TT phases are shorted together inside the GIS, the remote end of the test cable is effectively located at the same outdoor terminal position at the substation.)

Test phase R S T
Main insulation Main insulation Main insulation
Fault resistance Endless 0MΩ 0MΩ
Is it a fault? Intact Fault Fault

 

Step 2: Fault pre-location

01. First, the healthy R-phase cable was tested along its full length as a reference. As shown in Figure 1, the single cable length is 2,743 meters. The two distinct sinusoidal reflection waveforms in the middle indicate the positions of the insulated joints, while the weaker sinusoidal reflection near the end indicates the location of the straight-through joint.

 

02. The low-voltage pulse method is used to test the full length of the S-phase cable compared to the full length of the R-phase, as shown in Figure 2 below. The red waveform represents the S-phase fault waveform, while the black waveform represents the full length of the R-phase. It can be observed that the R-phase experiences a disconnection at the "red marker" position, approximately 417.9 meters from the GIS terminal, and the disconnection point coincides exactly with the position of the straight-through joint. The fault is suspected to be located at the straight-through joint.

 

Step 3: Cable Path Search

The cable path information is clear and does not require searching.

 

Step 4: Fault Location Precision

S phase:

01. After applying pressure to the S-phase, we went to the straight-through joint chamber to observe. The appearance of the joint had been inspected previously and showed no issues. However, when approaching the joint in the chamber, a faint discharge sound could be heard, leading to the suspicion that an internal insulation fault occurred at the joint.

 

02. It was decided to dissect the joint. As shown in Figure 3 below, the main end of the cable joint has been scorched, and the metal shielding is damaged. However, the cable itself is not disconnected, indicating that the fault affecting power transmission is not located here.

 

03. Upon reanalyzing the waveform shown in Figure 2 above, the test gain was increased, and the local cursor position was zoomed in, as shown in Figure 4 below. It was found that the disconnection waveform position does not exactly coincide with the straight-through joint position, but is actually about 15 meters apart.

 

04. After applying pressure to the S-phase cable, the fault location was pinpointed 15 meters before the joint. The equipment detected a distinct discharge sound, and the minimum acoustic time difference at the fault point was 5.8 ms. The fault location is shown in Figure 5 below.

 

05. Since excavation cannot be immediately carried out at this location and on-site verification is not possible, confirmation will be made after subsequent excavation. The S-phase fault point has been successfully located.

 

T phase:

01. The low-voltage pulse test waveform for the T-phase is also a full-length waveform, indicating that the T-phase has not experienced a disconnection, but rather a high-resistance grounding fault due to insulation breakdown. The pulse current method, used in conjunction with the high-voltage unit, is required for distance measurement. The fault distance was measured to be approximately 5430 meters, which exceeds the single-circuit cable length (TT-phase short circuit at the GIS), suggesting that the fault point is on the T-phase of the other circuit.

 

02. The testing end was switched, and the fault waveform for the T-phase of the other circuit was measured under pressure. The fault waveform is shown in Figure 6 below. One cycle of this waveform corresponds to a fault distance of 50 meters.

 

03.After removing the 30-meter reserved coil near the near-end station, the fault point was found near the cable terminal. After applying pressure, noticeable ground vibrations were felt at a certain location. Excavation was carried out randomly, and the T-phase fault point was successfully located, as shown in Figure 7 below.

 

04. After the cable at the fault point was sawed through, insulation tests were conducted on both cable sections, and both passed. The T-phase fault was successfully located.

 

    III. Test summary

    01. The insulation joint metal sheath is split and disconnected. The waveform at the joint is usually more distinct. In the case of a straight-through joint where the metal shielding is fully connected, the waveform reflection is weaker and harder to detect. At this point, the distance between each joint can be compared for judgment. Generally, the three segments of cables in a cross-interconnected large section are of equal length.

     

    02. Fault testing should carefully analyze multiple certifications. Until the fault is identified, all special situations are possible.

     

    03. This straight-through joint is the endpoint of a large section of cross-interconnected cables, and the metal sheath must be directly grounded. The metal sheath at the GIS end connected to it must also be properly grounded for protection. Otherwise, the sheath in that section will continue to heat up during cable current operation or during a short circuit to ground. This is because the single-core voltage generates induced voltage on its metal sheath, and the existence of the loop leads to circulating current, which in turn causes the cable to heat up. The reason for the failure of the metal shielding in both straight-through joints is due to this issue.

    Xianheng International Showcased Innovative Power Solutions at FIEE 2025 in Brazil